The Finance Ministry says it has spent only Rs. 96.8 billion, or 15.3%, of the total Rs. 632.4 billion mega development projects allocation for 2026 by end-June, and blames slow implementation by line Ministries rather than any shortage of funds (see box: Foreign-funded mega projects lag furthest behind).
The quarterly report by the Department of Project Management and Monitoring (DPMM), submitted to the Cabinet of Ministers recently, covers 210 projects that each cost over Rs. 1 billion. Spending reached just 39.3% of the Rs. 246.2 billion target for the
first half.
The findings raise questions over the Government’s ability to deliver the 2027 Budget, which President and Finance Minister Anura Kumara Dissanayake presented on 12 November as a shift from stabilisation to transformation. The Budget raises capital spending by 35% to Rs. 2 trillion, or 5.1% of GDP, from 4.1%, prioritising roads, railways, rural connectivity, logistics, and some social spending.
Capital spending has lagged well behind allocations all year. Treasury data show capital expenditure and net lending reached Rs. 276.6 billion in the first half, only 16.1% of the annual estimate of Rs. 1.72 trillion. Lower capital spending, together with a surge in revenue, helped the Budget swing to a surplus of Rs. 9.5 billion, from a deficit of Rs. 405.6 billion a year earlier.
The World Bank said in October that the Government had spent only 16.7% of its 2026 capital Budget and about 8% of the Rs. 500 billion allocated for Cyclone Ditwah reconstruction by mid-year. It attributed the shortfall to weak public investment management rather than a lack of funds. The 2027 Budget carries forward Rs. 260 billion of the cyclone allocation, which Fitch Ratings said went unspent in 2026 because of under-execution.
Analysts have also flagged the risk. “Key risk is execution, not funding,” CT Smith said in its assessment of the Budget.
The DPMM review reaches the same conclusion. “Although there was no delay in the release of funds from the General Treasury, financial utilisation remains low due to project activities not being implemented as expected,” the report said. Bills in hand, meaning payments due for work already done, stood at Rs. 12.5 billion.
The shortfall is starkest in the country’s largest road project. The Central Expressway’s Section 1, funded by China, was allocated Rs. 64.15 billion for 2026 but had spent only Rs. 2.88 billion by June, about 4.5%. Section 1 began in September 2020 and was due for completion in September 2024. It is now 50.5% complete, and its deadline has been pushed back four years to September 2028.
Section 3, funded locally, has spent Rs. 7.28 billion of its Rs. 30.5 billion allocation. It started in January 2016 and was due to finish in June 2024, but is 36.8% complete and now has a 2029 deadline. Together, the two sections account for about 15% of the total mega project allocation for the year.
At Ministry level, the Housing, Construction and Water Supply Ministry spent Rs. 9.53 billion against a 1H target of Rs. 48.93 billion, or under 20%. The Transport, Highways, Ports and Civil Aviation Ministry, which has the largest target, spent Rs. 33.66 billion of Rs. 83.58 billion. The Finance Ministry’s own projects performed best, spending Rs. 9.03 billion of a Rs. 10.87 billion target.
Of 47 projects scheduled for completion by end-June, only 10 had been finished. 20 projects made no physical progress during the quarter, and 62 were less than 40% complete.
The review also exposes weak discipline over deadlines. It found that 35 projects were still being implemented after their approved periods had expired, without obtaining formal extensions of time. Another 121 were running on formal extensions, and only 54 were within their agreed time frames. The report said the delays had pushed up costs and changed project scopes, hurting cost effectiveness and holding back benefits to the public.
“Overall project performance has not shown significant improvement, and a large number of projects are being implemented with extension of time,” it said, noting that this was despite earlier problems such as fund release difficulties and suspended foreign loans having eased.
The DPMM’s colour-coding system classified 32 projects as critical because of several time extensions, cost overruns, or other issues. A further 39 need special attention and 70 need interventions to deliver expected results. Only 58 were rated as progressing successfully or properly.
Several long-delayed projects stand out. Construction of the Pallekele Prison Complex began in January 2007 and was due to finish in December 2011. With 203 months of extensions, it is 79% complete and now has a December 2028 deadline. The Defence Headquarters Complex Phase 1, estimated at Rs. 65.45 billion, began in 2011 and was due in October 2016. It is 99.5% complete after 123 months of extensions and is rated critical.
The Indian-funded 10,000 Housing Program had reached only 10.32% physical progress against a target of 45%. It has spent Rs. 356.6 million of its Rs. 4.29 billion allocation for the year.
Of the 39 ongoing projects that are over 90% complete, 12 began before 2016, although they were originally meant to take three to six years. The report urged Ministry Secretaries to finish them without further delay. “This will create financial space for new public investments in accordance with the Government’s policies,” it said.
Contractor performance was the most common cause of delay, affecting 28 projects. It was followed by procurement delays in 22 projects, delays in third-party approvals in 20, and shortages of project management staff in 12. The report also cited short-term fuel supply restrictions, higher fuel prices, and difficulties in obtaining bitumen.
The DPMM also warned that weak exit strategies had left some completed projects without proper operations, staffing, or asset transfers. It said ‘the underutilisation or abandonment of such assets can be observed’ and that it would issue a circular requiring Ministry Secretaries to plan for project completion, handover, and sustainability.
During pre-Budget discussions, the President directed officials to improve the implementation of infrastructure programs. At the agriculture sector review, officials noted that delays in completing projects started in previous years had imposed a significant financial cost on the Government, and it was decided that projects that had missed implementation timelines would be reviewed.
The total estimated cost of the 210 projects is Rs. 3.7 trillion, and a further Rs. 1.8 trillion is needed to complete them.