Foreign-funded mega projects lag furthest behind

Monday, 23 November 2026 00:21 -     - {{hitsCtrl.values.hits}}


 

  • Foreign grant projects spend just 7.9% of Rs. 31.8 b allocation by June
  • Foreign loan projects use 14.6% of Rs. 377.2 b; domestically funded 17.6%
  • Scope changes, land acquisition, weather also stall projects
  • PIMEC handled fund-release issues on 18 projects in 2025

Foreign-financed mega projects are spending their allocations more slowly than those funded locally, the Finance Ministry’s Department of Project Management and Monitoring (DPMM) said in its review of the second quarter of 2026.

The 26 projects funded by foreign grants had spent Rs. 2.51 billion, or 7.9%, of their Rs. 31.8 billion allocation for the year by end-June. That was only 21.5% of their first-half target. The 66 projects funded by foreign loans spent Rs. 55.13 billion of Rs. 377.19 billion, or 14.6%, reaching 36.4% of their target.

The 116 projects funded by domestic funds performed best, spending Rs. 38.89 billion of Rs. 220.99 billion, or 17.6%, and 47.6% of their first-half target. Two projects financed by local bank loans spent Rs. 270 million of Rs. 2.43 billion.

Foreign financing problems have largely eased. “At present, all projects except one project for which foreign loan funds were suspended have been restarted,” the DPMM said.

Besides the main causes of delay, 11 projects were held back by changes of scope. Eight suffered from suspended disbursements or rising prices of construction and other materials, six from land acquisition delays, another six from climate and weather changes, and three from poor consultant performance.

To clear bottlenecks, the DPMM holds Integrated Quarterly Progress Review Meetings (IQPRMs) in line Ministries, with officers from other Treasury departments taking part. According to the DPMM’s Annual Performance Report 2025, 51 such meetings were held across 25 Ministries last year.

Issues that cannot be resolved at these meetings go to the Public Investment Monitoring and Evaluation Committee (PIMEC), set up under the Public Financial Management Act to take swift decisions on implementation problems. The PIMEC met 21 times in 2025. The most common problem it dealt with was the release of domestic or foreign funds, affecting 18 projects, followed by coordination among stakeholders in nine.

“The authorities implementing the projects should refer unresolved issues in the projects to the Committee for the purpose of obtaining appropriate solutions,” the DPMM said in its latest review.

It placed responsibility for delivering results on those running the projects. “Secretaries to the Ministries and Project Directors bear a significant responsibility in addressing this situation,” it said.